DMA Redesign
Why redesign a DMA? | Key Factors in DMA Design | Why Torquay?
Phase 1 | Phase 2 | Phase 3 | Results
Why redesign a DMA?
The cost of targeting and identifying leakage is increased in a poorly designed or maintained DMA. DMAs with a high property count or excessive numbers of meters become increasingly difficult to accurately target or report leakage. Long established DMAs may no longer fit the purpose they were designed for.
The significance of establishing the accuracy of source data is of paramount importance when designing DMAs.
We believe robust DMA designs offer better management and control ultimately leading to the reduction in real water losses from the system.
Key Factors in DMA Design
The designs should:
 |
Create separate trunk main DMAs |
 |
Reduce the numbers of import meters per DMA (ideally single feed) |
 |
Reduce the number of properties per DMA (<1500 approx) |
Further considerations during the design phase:
 |
Separation of reservoir supply areas |
 |
Operability |
 |
Existing PMAs and additional pressure reduction |
 |
Regulatory exposure (DG2) |
 |
Emergency contingencies (reduced reservoir capacity, pumping regimes) |
 |
Historic distribution problems in supply areas (high burst frequency etc.) |
 |
Seasonal demand |
 |
Future development |
 |
Water quality issues |
 |
Minimising capital expenditure (utilise existing meters and PRVs) |
 |
Continuing rehab on trunk mains |
 |
Large Commercial and Industrial users |
Why Torquay?
South West Water had identified the need to improve the accuracy of leakage reporting in some DMAs and Torbay had always been regarded as a difficult area to approach due to:
 |
Complexity of WIS design |
 |
High burst frequency |
 |
High percentage of brought forward DMAs |
 |
Lack of confidence in DMA boundaries |
 |
Lack of confidence in STRUMAP records |
 |
‘Patchy' local knowledge |
 |
Average of 5 import/export meters per DMA |
 |
High property count per DMA (1 DMA > 5000 & 6 DMAs > 2500 properties) |
Extensive rehabilitation in the area dovetailed perfectly with Leakage Control's desire to resolve the ongoing issue of brought forward DMAs and the project was commissioned to redesign Torquay (WIS 508) The original WIS Zone comprised of 16 DMAs and supplying 31000 properties.
Following consultation it was agreed to undertake a sluice valve survey. Due to the complexity of this area we needed to confirm the accuracy of existing GIS assets and initial consideration was given to surveying only DMA “parting valves”. It was felt this could still leave internal valve anomalies and a definitive “state of the system” was needed. As a by-product we would also address mains status and positions and abandoned mains during the course of the survey.
Exwater UK Ltd was tasked with co-ordinating the project. This would incorporate a Pilot Study, Valve Survey and DMA Redesign, 3 phases in all.
Phase 1 (Pilot Study) – to undertake a survey of 30% of all sluice valves in Torquay (WIS 508A/B).
The pilot study covered 14 sq/km (1000 valves) of both rural and urban areas. It was used to investigate the level of anomalies and determine whether there was a need to survey the whole WIS Zone. It revealed a high level of anomalies (>35%) which necessitated a survey of the remaining sluice valves (33 sq/km in total).
Phase 2 - Valve Survey
The valve survey was undertaken by 2 teams who completed a physical inspection of approximately 2500 sluice valves. All anomalies were noted such as incorrect records of size, position, orientation (open/closed/throttled), also where existing valves were not shown on GIS. All anomalies were addressed with the local Distribution Inspector and rectified to reflect the current operation of the network. All valve data was collated and presented to GIS for re-digitising. Once updated the modified GIS data was QA'd as a final check for accuracy.
Torquay survey results:
Valves Shown on GIS |
Valves Not shown on GIS |
Total Valves Surveyed |
GIS & Hydraulic Anomalies |
Anomalies as % of total |
2948 |
487 |
3433 |
1229 |
41.69% |
Phase 3 - DMA Redesign
The most important element of DMA design is having data that accurately reflects the network. Now that GIS was representative of the distribution network - designing could commence.
The designs were not conceived in isolation but jointly between Exwater UK Ltd, Distribution and Leakage departments. Leakage benefited from Distribution's specific knowledge of Torquay while Distribution gained a better understanding of Leakage requirements and constraints. As the dialogue expanded other departments offered valuable support to the project (O&M, Rehab, GIS, Developer Services, Asset Planning and Engineering Services).

Bespoke “Strumap” modelling packages were used to predict the suitability of designs. Prior to any ‘civils' work on a new DMA, parting valves were closed and the system was trialled. The area was closely monitored and where meters existed flow data was collected and analysed. Once designs were proven any outstanding civils work was completed and the new DMA commissioned. On successful completion of Zero Pressure Tests (ZPT) the new DMAs were signed over to Leakage Control and committed to the corporate reporting system. Finally WIS Zone Management Plans were compiled along with schematics for all the new DMAs.
Results
In brief the table below is a snapshot of the reported leakage immediately following design and implementation of the new DMAs.
WIS Zones |
Pre Design |
Post Design |
508A, 508B |
508A, 508B & 508C |
No. of DMAs |
16 |
28 |
Total WIS leakage |
5.40 ml/day |
3.46 ml/day |
Properties brought forward |
76% |
5% |
DMAs brought forward |
10 |
2 |
Since the completion of this project Leakage have benefited from reduced leakage, improved targeting for leak detection, robust data for reporting and with the introduction of “remote logging” greater transparency on the day to day operation of DMAs. Many more benefits were derived from the project with SWW continuing to apply this design ethos to further WIS Zones in Torbay. To date Exwater UK Ltd have undertaken further DMA redesign projects of WIS 506 (Brixham) and WIS 507 (Paignton) with WIS 509 (Newton Abbot) nearing it's completion.
Typical DMA MANAGEMENT PLAN
(You may need to to view this file).
In all, the project benefited through fully integrated client/consultant resource incorporating all criteria to meet the operational needs of both Leakage and Distribution Departments.
To find out more please contact us.
| Top of Page | |